Segment 1 Progress

The sidewalk pour is complete on Main St. from Highway 20 to Alameda Ave. East (segment #1).  Granite Construction is making great progress, just some finishing touches are left to complete.

On Monday, May 21 sidewalk work began on Main Street from JD Redhouse and Company to Chase Bank (a portion of segment 6).  Work will wrap up by June 22 in time for Frontier Days.

IMG_0124IMG_0125 (002)seg 1- 5-21-18

Thank You from Willits Head Start

We got a nice note from Willits Head Start program last week:

“I would like to give a huge shout out to The Willits Unified School District Bus Barn, Caltans District 1, and The Willits Police Department! Thank you for volunteering your time to come visit our classrooms today. You have all helped our children gear up for the summer ahead.

Alexis England from Caltrans stopped by to talk to us about staying safe during the road construction that is happening in our town, and The Willits Police Department came to talk with us about pedestrian safety. Thank you to all who have helped the future of our community learn a little more.”head starthead start 2

Sidewalk Construction Update:

IMG_0092 (002)

Work starts on Monday, May 7 on Segment #1 (Main St. from Hwy 20 to Alameda Ave East) and on Segment #4 (from Alameda Ave to California Street West side).

In these segments, there will be no parking on Main St. and a temporary pedestrian access route is set up.

All business will be open during construction.

Downtown Business Owners: find out which segment you are located in and the construction schedule- click link below

https://willitsbypass.files.wordpress.com/…/willits-sidewal…

PowerPoint Presentation

More construction timeline documents are available at the tab at the top of this page click on SideWalk Project Plans or the link below

https://wordpress.com/view/willitsbypass.wordpress.com

Get construction updates on twitter. Follow @WillitsMainSt

Or sign up for updates sent via text to your cell phone:

text-Follow WillitsMainSt to 40404. (case sensitive)

Willits Downtown Sidewalk construction has begun

The Willits Downtown Sidewalk Improvements construction project began this week.

The first phase is potholing and saw cutting all along Main Street from Highway 20 to Valley Street.  Potholing means the process of hand digging holes in the roadway to double-check that all the buried utility, water, fiber optic, and sewer lines are indeed at the depth utilities said they are.  This helps to avoid cutting or damaging the lines during construction.  The potholing is scheduled to be complete by May 4.

Saw cutting is the term used for making a cut through the old sidewalks in preparation for the actual demolition and removal work.  (See Sidewalk Project Plans tab on the top of this web page for approximate work dates for segments and segment maps)  Saw cutting is planned to complete by May 11.

Daily updates will be posted on twitter @WillitsMainSt

Or if you are not a twitter user and/or would like updates texted to your phone-

text follow WillitsMainSt to 40404.  (case sensitive)

 

Willits Downtown Sidewalk Improvements Open House

Caltrans and the City of Willits are hosting an informational open house for the Willits Rehabilitation and Relinquishment of Old Highway 101 on Tuesday, April 17 at Willits City Hall Community Room at 111 East Commercial Street, Willits.

The public is invited to drop in anytime from 5:30 to 7:30 pm.  Caltrans and other officials will be on hand to answer questions.  The project plans and tentative work schedule will be available for review.  Merchants and interested residents can learn how to sign up for construction updates.

The construction contract was awarded to Granite Construction.   The project is tentatively scheduled to start at the end of April and be completed by the end of November 2018.

This project will bring the road into good repair and then turn it over the City of Willits and the County of Mendocino.  Phase one work includes upgrading sidewalks and curbs to current accessibility standards, upgrades to existing drainage facilities, slurry seal, and restriping.  Phase two includes grinding, paving and restriping the roadway.

Questions about the total cost of the Willits Bypass

WillitsAerial1In response to questions regarding the total cost of the Willits Bypass Project, District Director Matt Brady has the following statement:

“Although the Willits Bypass is one of the most important interregional projects for the north coast, eliminating delays on U.S. Highway 101 and easing congestion for residents, the project did have its challenges. Bypass construction costs, including the associated right-of-way, mitigation, and relinquishment projects, did rise to $300 million as protests, permitting issues and bird-nesting season delayed the project. This was previously shared at public California Transportation Commission meetings in 2014 and through press coverage. Support costs including staff and consultants added another $159 million, bringing the total cost to $459 million. Those support costs include assessing the environmental impacts of over 30 potential routes, the development of the most extensive and detailed mitigation plan in Caltrans’ history, and then rewriting large sections of that mitigation plan to resolve issues with evolving requirements from permitting agencies. Caltrans did mistakenly report $300 million as the total cost of the project as part of our opening day ceremony, however, as indicated previously, it only included construction costs, mitigation, etc., which was not the “total” cost, and this was an oversight on our part.”

Summer Traffic Showing Willits Bypass a Success

Screen Shot 2016-11-02 at 6.26.32 PM

The south interchange of the Willits Bypass the day before opening to traffic, November 2, 2016.

Schools are out, summer is here, and the Willits Bypass is successfully handling the extra traffic during its first summer of use.  The long traffic backlogs and delays which have been the norm for decades have not reappeared.  The April traffic counts show that on average more than 4,000 vehicles per day are using the bypass and not creating the previously reoccurring congestion in downtown Willits. As summer traffic peaks even higher the bypass is anticipated to continue to easily handle the traffic.

“The California Highway Patrol is extremely pleased with the efficiency of having the Willits Bypass,” said CHP Lieutenant Randy England, Garberville Area commander. “We have seen the impact of safer roadways and less congestion during busy weekends.” Those busy weekends so far this year have included Memorial Day, the Redwood Run, as well as Humboldt State University’s graduation. In the past CHP would have added extra officers in the Willits area during these weekends, manually directing drivers to keep traffic moving during severe backups. Thus far, there has been no need for traffic control assistance. Continue reading

Public Invited to Willits Bypass Completion and Memorial Bridge Dedication Ceremony

Caltrans invites the public to join with us on Thursday, November 3, to celebrate the opening of the Willits Bypass Project.  The ceremony begins at 11 a.m., and parking opens at 10 a.m. The ceremony will also include the dedication of the 1.1 mile long viaduct as the Jesse D Pittman S01 Navy SEAL Memorial Bridge. The celebration will be held on the new highway, at the south end of the viaduct. Entry will be through the south interchange, just south of Willits. Follow the signs for “Special Event” to be directed to parking.willitsmap_completion_for_public

Continue reading