WILLITS BYPASS PROJECT
CONSTRUCTION UPDATE
SEPTEMBER 2016
The following is a summary of the construction activities that have been completed up to September 20, 2016
South Segment (Beginning of Project to Center Valley Road) – STA”A”96+00 to 149+00 (3.3 miles):
- Paving HMA complete with the exception of Stamped gore paving at ramp gores. Completion is expected by October 01.
- Northbound traffic is currently routed onto the bypass to the new Hwy 20 exit and back to Willits. Traffic will be in this configuration until the bypass opening.
- Striping and delineation operations are in process. Completion is expected by the middle of October.
- The Drainage systems are complete and functioning.
- Electrical facilities for message boards and CCTV cameras are currently being installed. Completion is expected by the middle of October. Street lighting is operational.
- Roadway signs are currently being installed and anticipated to be completed in early October.
- All structures are complete.
- Contractor is working on miscellaneous punchlist items and cleanup to complete construction. Completion is anticipated to be complete by the end of October.
Floodway Viaduct – STA “A” 149+00 to 167+50 (1.2 miles): Continue reading